Skip to content

Al Yousr Seawater Reverse Osmosis desalination plant

Project Summary

In September 2016, Misr for Engineering Works successfully played a vital part in constructing the first mega SWRO of its kind in Egypt, Al Yousr SWRO. 

Al Yousr SWRO was launched by the Egyptian Government as an integrated solution for the potable water shortage crisis in the city of Hurghada. It utilizes two pass systems with a total capacity of 80000 m3/day, a capacity that’s sufficient enough to serve a population of +500,000 residents. 

Misr for Engineering Works was responsible for the successful execution of the lifting processes for the whole project. What makes our work stand out in terms of quality and speed was our 30+ meters span double girder crane in two parts connected with our own design for bolted connection. 

Beside that, we utilize our Double girder EOT with capacity up to 10 tons, our Single Girder EOT with capacity up to 5 tons, and other supporting lifting equipment that were – all together –  key factors for the project progress.

Project Info

Sector:

Water treatment plant - desalination

Date excuted:

September 2016

Uniqueness:

30+ meters span double girder crane in two parts connected with our own design for bolted connection.

Link:

Summary of Supplies

Type
Capacity
Quantity
Double Girder EOT
10
2
Single Girder EOT
up to 5 ton
2
Monorail
up to 3 ton
3
Jib Crane
Gantry Crane