Port Said Tunnels are among the significant national projects facilitating the movement of containers and encouraging the establishment of factories in East Port Said. In October 2020, three tunnels were majorly underway under the Suez Canal in Port Said.

Misr for Engineering Works contributed with its 1.5 and 2-ton monorails in the drilling and construction work. With a cost exceeding 18 billion pounds for the projects, two of the tunnels are for cars, while the third tunnel is for the railway, aiming to cross trains to connect the east and west of the canal.

معلومات المشروع

قطاع:

Drilling & construction work

تاريخ استبعاده:

أكتوبر 2020

التفرد:

One of the important national projects that helps facilitate the movement of containers and encourage the establishment of factories in East Port Said.

حلقة الوصل:

ملخص التوريدات

نوع
سعة
كمية
العارضة المزدوجة EOT
عارضة واحدة EOT
مونوريل
1.5 ton
2
الجيب كرين
2 طن
2
رافعة جسرية
arالعربية